Worked example: multi-let office, Manchester — 320 kWp, landlord + tenant PPA
Modelled scenario. This is not a real project or a real client. All figures are illustrative assumptions, not a quote or a prediction for any building.
| Scenario type | Multi-Let Commercial Buildings |
|---|---|
| Illustrative location | Manchester |
| Assumed system size | 320 kWp (modelled) |
| Ownership structure | Common-parts supply + landlord–tenant PPA + green-lease addendum |
| Modelled annual generation | 304,000 kWh/yr (modelled) |
| Modelled annual value | £71,000/yr (modelled, landlord + tenant blended) |
| Modelled simple payback | 5.8 years |
| Assumed EPC movement | D → B (modelled) |
This is a modelled worked example, not a real project and not a real client. It is not a case study. The building, the fund and every figure are illustrative assumptions chosen to be realistic, so you can see how the ownership and lease mechanics fit together. It is not a quote, and it is not a prediction for any specific building. The structuring is the point, not the address.
Assumptions
- A 1980s multi-let office in Manchester M2: roughly 4,200 m² of lettable space across six floors, EPC D, three tenants on full repairing and insuring (FRI) leases with around four to six years left to run.
- A large, unshaded flat membrane roof in good condition, carrying a 320 kWp array.
- A typical UK yield of roughly 950 kWh/kWp, giving about 304,000 kWh a year.
- A PPA price of 22p/kWh against a grid rate of around 27p.
- Costs are ex-VAT. Ordinary commercial premises are standard-rated at the 20% rate of VAT, which is normally recoverable if the business is VAT-registered and making taxable supplies. A 0% rate applies only to residential accommodation and buildings used solely for a relevant charitable purpose (VAT Notice 708/6).
- Blended annual saving of about £71,000 and a payback of about 5.8 years, both modelled.
The challenge
Picture a regional property fund that owns the building described above. The roof is physically ideal for solar.
The problem in this scenario is not the roof. It is who pays and who benefits. Under FRI leases each tenant buys their own electricity directly from their supplier, so a rooftop array does nothing for the landlord’s own position unless the power has somewhere to go. The landlord’s only metered consumption is the common parts (lifts, landlord lighting, the comms room, the ventilation plant), which on its own could not absorb a 320 kWp system. Funding the install through the service charge is not a way out: the schedule would not normally allow capital improvements of this size to be recharged to sitting tenants, and three tenants paying for an asset the landlord retains is a hard conversation to win.
Underneath that sits the asset risk. EPC D is lawful to let today, but the building in this scenario is a long way from the proposed EPC B by 2031 standard now under consultation (the government’s interim response of 18 June 2026 confirmed B by 2031 as a proposal for privately-rented non-domestic buildings over 1,000 m², subject to secondary legislation and a cost-effectiveness test). A fund’s net-zero pathway and its next valuation would both flag a building like this as exposed.
The structure
A project like this starts with the half-hourly (HH) data, not the roof. Twelve months of HH consumption for the landlord supply, plus modelled data for the three tenant supplies, gives a real load shape across 14 sub-meters rather than a guessed annual figure. In this scenario that shows two things: the common parts have a steady daytime base load, and two of the three tenants are daytime-heavy office occupiers whose demand lines up well with a solar generation curve.
That shapes a 320 kWp system feeding three routes through the split incentive:
- Common-parts supply. Solar offsets the landlord’s own metered consumption first, at the landlord’s commercial rate. This is the cleanest economics on the site because there is no counterparty: the landlord generates and consumes behind its own meter.
- Landlord–tenant PPA. The balance is sold to the two daytime-heavy tenants through a behind-the-meter power purchase agreement at 22p/kWh against a grid rate of around 27p. The tenants pay less than the grid for the solar they use; the landlord earns a margin on power it would otherwise export at a much lower rate. Any genuine surplus is exported under the Smart Export Guarantee as a top-up, not the headline.
- Green-lease addendum. Both PPAs are wrapped in a green-lease addendum so the arrangement survives a change of occupier, sets out metering and data-sharing, and aligns the building’s ESG reporting between landlord and tenant.
For the detail on why this matters and how the routes compare, see the guide to the split incentive solved.
The build
The model assumes a 320 kWp system on the existing flat roof using ballasted, non-penetrative mounting to protect the membrane warranty. Because the array sits above the G98 limit of 16A per phase, the real timeline driver would be the DNO G99 connection process, not the panels, so that application would go in early and run in parallel with everything else. Rooftop solar of this size is permitted development under Class J (the 1 MW cap on commercial rooftop was removed on 21 December 2023), so planning would be a 56-day prior approval on design and glint-glare rather than a full application.
Metering is the unglamorous heart of a job like this. The design includes generation and export metering plus sub-metering so that each tenant’s solar consumption is measured independently and billed transparently under the PPA, with no estimates and no apportionment arguments. As a general fact, rooftop solar and co-located storage are exempt from business rates in England (100% to 31 March 2035), so the array would not add to the rates bill.
The modelled outcome
The 320 kWp system generates around 304,000 kWh a year in the model, at the assumed yield of roughly 950 kWh/kWp. Self-consumption across the common parts and the two tenant PPAs sits in the daytime-shift band, with the SEG export as a small top-up. The blended annual saving, landlord margin plus tenant bill reduction, comes to about £71,000 a year on the stated assumptions, for a payback of around 5.8 years on this illustrative build.
The asset move matters as much as the cash. Solar typically lifts a commercial EPC by one to three bands rather than guaranteeing a fixed jump; in this scenario, combined with lighting and controls assumed to be already in train, it takes the whole building from EPC D to EPC B. That would move the MEES risk rating from red to green against the proposed 2031 standard and remove the stranding flag from the fund’s net-zero pathway and its next valuation.
The general pattern for multi-let offices is that the engineering is straightforward, and the value is unlocked by getting the supply route and the lease structure right so the right party pays and the right party benefits. The numbers only work for everyone when the PPA and the green-lease addendum are in place alongside the metering.
If you own or manage a multi-let building and want to see whether the load shape and lease structure could support a project like this, read about multi-let commercial buildings, then request a quote: we reply to your enquiry by email.
Get a quote for your property
Tell us about the building and who pays the energy bills. We reply by email.